Task 1 Project Management (milestone)
- Discuss comments and revisions to Phase 6a draft scope and cost
- Need to finalize PR #323 to fix min inbound departure times
- MWCOG votes for autocalculating chunksize improvements because its model would be run by several regional partners with different machines, needs, use cases, etc.
Task 2 Strategic Planning (milestone)
- Reviewed relevant information from peer projects like matsim, astropy, visioneval
- Making some progress on the strategic development and contribution plan outline here
Task 3 Two Zones (milestone)
- Need to work on documentation
Task 9 Estimation Mode (milestone)
- Need to finish updating the examples and tutorials to use the example distribution system
Task 10 Support for Three Zone Systems and TVPB (milestone)
- We're working on the design for downstream models to use the new data structures
- We're working on building / designing examples (such as expression files, settings, and test example data) to make use of the new data structures
- We all need to think about a more complete test example soon to really exercise performance, memory usage, and other issues