- Admin
- GitHub 2FA status
- Phase 7 Closeout - all oustanding tasks should be finished by the end of the week (relatively small things are left) so that full tests can be run and an official release of ActivitySim for Phase 7 available shortly after that.
- Scoped Tasks
- Additional Items
- Memory Profiling Final Report
- Joe noted that it would be good to have a little more emphasis on prioritizing/sequencing for the recommendations/next steps.
- *Comments from the consortium are due by January 20.
- Phase 8 Spinup?
- Joe synthesized discussions from the partners along with scoring/ranking and sent out the list of proposed priorities for Phase 8 funding to the consortium partners.
- Joe is still waiting for consensus from partners but have proceeded with developing scopes of work as proposed. Joe will take silence as consent to the proposed Phase 8 scoping.
- Next Meetings
- Cancel 1/5 and 1/10 meetings
- Tentatively keep 1/12 meeting, will cancel if needed.
- Phase 8 scoping should be available by then for discussion, if needed.
- Jeff to extend meetings past February, through another year.