Project Meeting 2016.10.07
Ben Stabler edited this page Oct 8, 2016
·
13 revisions
- Task 10 Full Model Run amendment is signed and executed
- We've spent 75 percent of the project budget to date
- Which is 85 percent of RSG's budget
- We'll likely stop work in November as a result
- Elizabeth will do her review in November
- OSG's budget will be reallocated to RSG for continuing work on Task 10
- The contract amendment is working its way through the member agencies
- Hope to start again in January
- Clint will work on the draft scope of work in the meantime
- Clint may be able to fund some ActivitySim related work under his on-call and will coordinate with the team
- For remaining work, we will continue to fix the current implementation - Task 10
- This means Task 8 mode choice logsums will need to be moved to next year's contract
- Bill to check on the contract to see if an email NTP is ok for moving Task 8 to next year and using the budget for Task 10
- We're going to meet up at TRB again this year
- CDAP has been completely re-implemented in a vectorized fashion as described in #116
- Tests and source code documentation are complete as well
- 370k HHs runs in 5 minutes without threading! This is very promising and is a major milestone for this project.
- Results compared to the existing MTC TM1 calibration by person type and M,N,H look pretty good. Only preschool persons are significantly different.
- Next steps
- Update the website documentation
- Run it on the full example
- I'll review in detail