ActivitySim work is done in Phases. Phases are typically six or twelve months in length and often start in the summer. This page provides an overview of the current phase of work.
Phase 6b started in June 2021 and the Phase 6b Scope of Work consists of the following tasks:
- Task 1 Project management
- Task 2 Vehicle type model
- Task 3 Software development tools
- Task 4 Visualization
Task Discussions Schedule
- Task 4 Visualization - June 29th
- Task 2 Vehicle type model - July 13th
- Task 3 Software development tools - July 20th
- Task 4 Visualization Progress - July 29th
- Task 2 Vehicle type model design update - August 17th
- Phase 7 scoping - August 24th
- Phase 7 scoping - August 31st
- Phase 7 scoping - September 2nd
- Cancel - September 7th
- Phase 7 scoping - September 9th (and Joe manages the call)
- Task 4 Visualization Progress - September 14th
- Task 2 Vehicle type model - September 21st
- Task 3 Software development tools - September 28th
The phase 6b meeting notes are on the Meeting Notes page.
During phase 6b, the following special topics will be added as new pages to the wiki: