-
-
Notifications
You must be signed in to change notification settings - Fork 716
New issue
Have a question about this project? Sign up for a free GitHub account to open an issue and contact its maintainers and the community.
By clicking “Sign up for GitHub”, you agree to our terms of service and privacy statement. We’ll occasionally send you account related emails.
Already on GitHub? Sign in to your account
Overview: May 2020 Sprint #589
Comments
New website progress
New docs include the following:
Hoping to deploy the new website over the coming weekend. We're down to about 18 issues and 3 PRs. When we started, I think it was 30 issues and 9 PRs. |
The new re-frame website is now up at: http://day8.github.io/re-frame/ The re-frame logo has been tweaked. See it here: And a release candidate for 1.0.0 is also out Also, we're now down to about 16 issues and 2 PRs. Now we begin on the meatier issues. |
The task of addressing meatier issues is now slightly delayed.
We are down to 13 open issues and 2 PRs, which is a numerical measure of some success. |
Many improvements to the docs have been made recently. Too many to mention but some are notable:
Also:
Numerically, we're at 13 issues and 3 pull requests. |
Isaac and I are doing a three-week-long sprint on re-frame - starting 4th May. Isaac's time is being paid for by ClojuristTogether funding. My time is paid for by Day8. So between us, we have about 6 man-weeks.
At a high level, the strategy is:
This will likely take longer than six man-weeks. And then there will be necessary adjustments to re-frame-10x. To quote a line from the movie
Get Shorty
"This is only the second day, and we're already two weeks behind." But, one step at a time, let's just see how we go.I will update this issue with new thoughts as we go. We will probably engage with the community via the clojurians
#re-frame
channel. If you are interested in the process, please keep an eye out there.The text was updated successfully, but these errors were encountered: